Two papers sit behind almost every other approval a school needs: a fire safety certificate and a building safety certificate. Both run out, both are asked for again at every renewal, and both are checked hardest after an accident somewhere else. Here is who gives each one, how to apply in Rajasthan, and what the inspector will look at.

By · Published · 14 min read

Short answer

A school needs two separate certificates. The fire safety certificate, commonly called the fire NOC, is issued by the fire authority; in Rajasthan that is the urban local body, through the Fire NOC service on the Local Self Government department's online portal, after a fire officer inspects the building. The building safety certificate is issued by a government engineer; CBSE asks for one from an officer not below the rank of Assistant Engineer in the PWD. The Supreme Court, in Avinash Mehrotra v. Union of India (2009), directed that schools be built to the safety norms of the National Building Code before recognition or affiliation, and that every existing government and private school install fire extinguishing equipment. CBSE also requires valid copies of both certificates in a school's Mandatory Public Disclosure and on its OASIS return.

Two certificates, two offices

Fire safety certificate and building safety certificate compared
Fire safety certificate (fire NOC)Building safety certificate
What it saysThe building meets fire prevention and fire safety requirementsThe structure is safe to use as a school
Who issues itThe fire authority. In Rajasthan, the urban local body (municipal corporation, council or board) through its fire officerA government engineer. CBSE's OASIS form asks for one issued by an officer not below the rank of Assistant Engineer in the PWD
What CBSE calls it"Valid fire safety certificate issued by the competent authority""Valid building safety certificate as per the National Building Code"
How it is checkedInspection of extinguishers, exits, stairs, wiring, kitchen, labs and fixed fire-fighting equipmentInspection of the structure: every block and every floor in use
How long it lastsUntil the validity date written on it; then renewalUntil the date written on it, or until the building is altered; then a fresh certificate

One does not replace the other. A fire officer does not certify the roof slab, and an engineer does not certify the extinguishers. A letter from the company that sold or refilled your extinguishers is neither: both CBSE rows ask for a certificate from the authority, not from a vendor.

Is a fire NOC mandatory for a school?

For practical purposes, yes. Three separate things ask for it.

  • The Supreme Court. In Avinash Mehrotra v. Union of India, decided on 13 April 2009, the Court directed that before granting recognition or affiliation, governments must ensure the school building is constructed according to the safety norms in the National Building Code of India. The safety standards the Court set out include a mandatory fire safety inspection and a no-objection certificate before a school is established or allowed to continue, and a structural stability certificate before permission is granted.
  • State recognition. A new school's recognition file asks for building safety and fire safety certificates, and inspectors ask for these first (see how to start a private school in Rajasthan). Read the current year's recognition order for the exact list, because it changes.
  • CBSE. The Mandatory Public Disclosure format (Appendix IX) has a row for each certificate, and both must be valid and self-attested. The yearly OASIS return asks the school to upload both certificates and enter the fire safety certificate's valid-till date. They are also part of an affiliation or extension application on SARAS.

In June 2024 CBSE sent schools a fire safety advisory, as reported: hold regular fire drills, carry out structural and non-structural fire safety audits, keep extinguishers and alarms checked, renew the fire safety certificate before it expires, store flammable and toxic material in the chemistry lab under strict norms, follow local building bye-laws, and train students and teachers. Schools had to file an action-taken report on OASIS. Treat that list as the standing expectation.

Whether a small single-storey school in a village needs a formal fire NOC under local law, and from whom, depends on where it is: urban local bodies cover towns and cities. If your school is outside municipal limits, ask the nearest fire station or the district administration in writing which office will inspect and certify. Do not assume the answer is "nobody".

What the Supreme Court directed in 2009

The case followed the 2004 fire at a school in Kumbakonam, Tamil Nadu. The fire began in a thatched kitchen where the midday meal was being cooked, spread to the thatched roof over the classrooms, and the roof came down on the children. The Court records that 93 children died. It held that the right to education includes the right to a safe school, and gave these directions:

  1. Before granting recognition or affiliation, state governments and union territories must ensure that school buildings are safe and built according to the safety norms in the National Building Code of India.
  2. All existing government and private schools shall install fire extinguishing equipment within six months.
  3. School buildings are to be kept free from inflammable and toxic material; if storage cannot be avoided, it must be done safely.
  4. The structure is to be evaluated periodically. Engineers and officials must follow the Building Code strictly, and a safety certificate is to be issued only after a proper inspection. Dereliction of duty should attract disciplinary action against the officials concerned.
  5. School staff are to be trained to use the fire extinguishing equipment.

That fourth direction is why a careful engineer or fire officer will not sign from the office chair. Plan for a real visit.

How to apply for a fire NOC in Rajasthan

Rajasthan's Local Self Government (LSG) department runs an online Fire NOC service on its LSG Online portal. The portal describes the fire NOC as issued by the department, and it lists a Fire NOC service and a Fire NOC Renew entry, a citizen manual, sign-in through Rajasthan SSO, a page to verify a fire NOC certificate, and a helpline. Start there, and read the citizen manual on the service page before filling anything.

The steps below are how published guides describe the process. Screens and menu names change, so follow the portal's own manual where it differs.

  1. Create or use the school's Rajasthan SSO ID. Use an ID that belongs to the school or trust, not to one employee.
  2. From SSO, open the LSG online service and choose Fire NOC (new) or the renewal option.
  3. Choose the urban local body in whose area the school stands. The application goes to that body's fire officer.
  4. Fill in the building details and the fire-fighting arrangements you have, and upload the documents.
  5. Fire officers inspect the premises. Guides say the inspection report is filed online within about seven days.
  6. Pay the fee the portal generates. The amount is worked out by the portal for your building; ask the fire office if it is unclear.
  7. When approved, download the certificate from the portal. Guides put the whole process at up to about 30 days; allow more.
Documents usually asked for with a fire NOC application
DocumentNote
Site plan and floor-wise plansEvery floor, plus basement and terrace if any, with section and elevation
Sanctioned building planThe plan as approved by the local body or development authority
Building detailsHeight, floors, built-up area, use of each floor
Fire-fighting details and photographsExtinguishers, hose reels, tanks, pumps, alarms as installed and working
Certificate from a fire consultantWhere the fire office asks for one
Proof of ownership or lease, and the school's registrationIn the name of the school, trust or society that is applying

The list is drawn from published guides, not from an official checklist we could open. Ask the fire office of your local body for its current list before you scan anything.

Covering letter to the fire officer

To The Fire Officer [Name of municipal corporation / council / board] Subject: Application for fire NOC [new / renewal] for [School name], [address] Sir/Madam, We have applied online for a fire NOC for our school building. Application number: [number], dated [date]. The building has [number] blocks and [number] floors, and is used for classes [from] to [to], with about [number] students. We request an inspection at an early date. Our contact person on site is [name, designation, mobile]. The building plans, fire-fighting equipment list and maintenance records will be kept ready for the inspecting officer. Yours faithfully, [Name] Principal / Manager, [School name] [Date and seal]

How to get the building safety certificate

CBSE has a set format for this certificate in its affiliation documents, and its OASIS form labels the upload as a building safety certificate issued by an officer not below the rank of Assistant Engineer in the PWD. For a CBSE school in Rajasthan that means writing to the Public Works Department office for your area. For state recognition alone, check the recognition order for which engineer the department accepts.

  1. Download the current building safety certificate format from the CBSE affiliation (SARAS) website, so the engineer signs in the wording CBSE expects.
  2. Write to the PWD office for your area asking for an inspection, attaching the sanctioned building plan and a list of every block with its number of floors.
  3. Keep ready the structural drawings and the original structural engineer's or architect's papers, if you have them. The inspecting engineer may ask for tests on an old building.
  4. Walk the engineer through every block and floor that students or staff use, including the terrace, staircases, basement and any later additions.
  5. Check the certificate before you leave the office: school name and address exactly as in the affiliation papers, every block and floor listed, the officer's name, designation, seal and date, and the validity period if one is given.

Get a fresh certificate whenever you add a floor, a block or a major alteration. A certificate that describes two floors does not cover a school that now has three.

In March 2025, after a slab collapse at a government school in Bikaner, the Rajasthan education department issued safety guidelines saying, as reported, that schools may use their buildings only after receiving a safety certificate from local authorities, that premises must be free of flammable and poisonous material, and that cooking and other fire-related work must be done at a safe distance from the main building.

What inspectors look for

The National Building Code's part on fire and life safety is the yardstick: the Supreme Court pointed to it, along with the Indian Standard on fire safety in educational buildings. The fixed equipment a building needs under the Code (hose reels, hydrants and risers, pumps, tanks, alarms, sprinklers) goes up with the building's height and floor area, and the Code has tables for the number of extinguishers and the quantity of water. We are not quoting those figures here: your fire officer will apply the Code and the local bye-laws to your building, and that written list is the one to follow.

What to walk through before the inspector does
AreaWhat is checked
ExtinguishersISI-marked, the right type for each place, mounted where they can be seen in every block, refilled and within date, with a service record
Exits and corridorsEnough exits for the number of children, doors that open easily, nothing stored in corridors, exit signs, an evacuation plan on each floor
StaircasesStaircases used as escape routes meet the Building Code, are clear of furniture and scrap, and are not locked during school hours
ElectricalNo old or exposed wiring, proper earthing and breakers, no overloaded boards, no high-tension line over or close to the school
Kitchen and canteenAway from classrooms, gas cylinders stored safely, no thatch or other material that burns easily
LaboratoriesChemicals labelled and locked, flammable stock kept low and stored safely, gas lines and burners in order, an extinguisher and first-aid box in the lab
Water and fixed equipmentA water tank kept for fire-fighting with its own piping and hose reels where required, and whatever hydrants, pumps or alarms the building's height calls for, all working
Alarm and drillsA fire alarm or bell that is heard on every floor, emergency numbers displayed, mock drills held and dated
PeopleStaff trained to use the extinguishers, and a named person in charge on each floor
StructureRoof and walls of non-combustible material, no cracks or seepage left unattended, younger classes on the lower floors

OASIS asks the same things as yes-or-no questions: whether the school has fire alarms, fire extinguishers and water sprinklers, whether fire safety audits and mock drills have been done, the date of the last drill, and whether students and teachers have been trained. Answer them from records, not from memory.

This is the certificate side of safety. The routine side, a quarterly walk of the whole campus with a signed report, is in our school safety audit checklist.

Validity, renewal and where to upload

Read the validity date on your own fire certificate; that date is what counts. Published guides on Rajasthan say a fire NOC is valid for one year and renewed every year, but we could not find a validity period published on the LSG portal itself, so confirm it with your fire officer. For the building safety certificate, go by the period the engineer writes on it, and by whether the building has changed since.

  • Start the renewal well before the date. An inspection, a list of corrections and a second visit can easily take more than a month.
  • Keep one register with each certificate, its number, issuing office, date of issue and valid-till date. Put the renewal start date in the school calendar.
  • When a new certificate arrives, replace the copy on the school website's Mandatory Public Disclosure page the same week, self-attested by the Chairman, Manager or Secretary and the Principal.
  • Update the fire safety valid-till date and upload both certificates in the next OASIS return, and use the current copies in any SARAS application. Check the current SARAS circular for the date by which certificates must be valid.
  • Keep the inspection reports and the list of corrections with the certificate. After an incident, they show what the school was told and what it did.

How Chalkbell helps

Certificates come from the fire office and the engineer; software cannot issue them. Where Chalkbell helps is the day-to-day part: the school sends a notice about a fire drill or a safety change to every parent of a class or the whole school and sees who has read it, and the day's attendance tells the office how many children should be standing at the assembly point. See the school app for parents. Book a demo

Common questions

Is a fire NOC mandatory for a school?

In practice, yes. The Supreme Court in Avinash Mehrotra v. Union of India (2009) directed that schools meet National Building Code safety norms before recognition or affiliation and that all existing schools install fire extinguishing equipment. CBSE requires a valid fire safety certificate from the competent authority in its Mandatory Public Disclosure and on OASIS. Check with your local body or district administration which office certifies your building.

Who issues a fire NOC for a school in Rajasthan?

The urban local body for the area, through its fire officer, using the Fire NOC service on the Local Self Government department's online portal, which is reached through Rajasthan SSO. Schools outside municipal limits should ask the nearest fire station or the district administration in writing.

Who issues the building safety certificate for a CBSE school?

A government engineer. CBSE's OASIS form asks for a building safety certificate issued by an officer not below the rank of Assistant Engineer in the PWD, in the format CBSE gives in its affiliation documents. It should list every block and floor the school uses.

How long is a school's fire NOC valid?

Until the validity date printed on it. Published guides say a Rajasthan fire NOC is valid for one year and renewed annually, but the period is not published on the state portal, so confirm it with the fire officer. CBSE has told schools to renew the fire safety certificate before it expires.

Is a letter from the fire extinguisher supplier enough?

No. CBSE asks for a fire safety certificate issued by the competent authority, which means the fire authority after an inspection. A supplier's installation or refilling letter is a maintenance record to keep in the file, not a certificate.

What did the Supreme Court say about school fire safety?

In 2009, after the Kumbakonam school fire, the Court directed that school buildings follow National Building Code safety norms before recognition or affiliation, that every existing school install fire extinguishing equipment within six months, that buildings be kept free of inflammable and toxic material, that safety certificates be issued only after proper inspection, and that staff be trained to use the equipment.

Sources

  1. Supreme Court of India: Avinash Mehrotra v. Union of India, 13 April 2009 (Indian Kanoon)
  2. Rajasthan Local Self Government department: Fire NOC online service
  3. CBSE Circular No. 1/2026 with Appendix IX, rows for building and fire safety certificates (copy hosted on a school website)
  4. CBSE OASIS 6.0 infrastructure form, as filled by a school (shows the certificate and fire safety fields)
  5. TeamLease RegTech: CBSE advisory for fire safety compliance in schools, 5 June 2024
  6. Udaipur Times: mandatory safety guidelines for Rajasthan schools, 1 Mar 2025
  7. IndiaFilings: Rajasthan fire licence, steps and documents (guide, not official)
  8. CalcGuru: Fire NOC in Rajasthan, what the official documents do and do not say (guide, not official)

Related on Chalkbell

More from the blog

See it with your school's data.

Leave your number and we'll call you back the same working day, in Hindi or English.

WhatsApp us